A team repeatedly provisions a new laptop for a joiner using a fully documented, well-rehearsed procedure whose risk was assessed once when the procedure was written. How should each individual provisioning be handled?

ITIL 4 Foundation, objective 7. Seven ITIL practices in detail medium

Draft — not checked yet. This question was written from the published exam objectives and cites the clause it comes from, but nobody has yet read it against that clause and signed for it.

It is kept out of search results and out of mock exams until they have. Read the source below before you take the answer as settled.

The options

Correct As a standard change, implemented under the authorisation already granted to the documented procedure

Correct. A standard change is pre-authorised: the risk assessment and authorisation were done once, for the procedure, so each instance needs no fresh authorisation.

Not correct As a normal change, assessed and authorised individually each time it is requested

Wrong. Putting a low-risk, repeatable, fully documented activity through individual assessment is exactly the waste that the standard change type exists to remove.

Not correct As a standard change, but with the change authority re-confirming authorisation on each occurrence

Wrong, and this is the most tempting distractor. Re-authorising each occurrence contradicts the meaning of 'pre-authorised' and would make the standard change type pointless.

Not correct As an emergency change, because provisioning must be completed before the joiner's start date

Wrong. A known deadline is not an emergency. Emergency changes are for situations that must be resolved as soon as possible, such as restoring a service or applying an urgent security fix.

Why

Standard changes are low-risk, well-understood, fully documented and pre-authorised. The risk assessment happens once, when the procedure is created and approved; individual instances then proceed without further authorisation, and are often initiated as service requests. Requiring per-instance authorisation would defeat the purpose of the category.

Where this comes from

Cited
ITIL 4 syllabus clause 7
What it says
Standard changes are low-risk, pre-authorised changes that follow a documented procedure and need no additional authorisation per instance.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 7 and space the ones you get wrong.

Practise ITIL 4 Foundation