A team repeatedly provisions a new laptop for a joiner using a fully documented, well-rehearsed procedure whose risk was assessed once when the procedure was written. How should each individual provisioning be handled?

ITIL 4 Foundation, objective 7. Seven ITIL practices in detail medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

How these questions are written — where each question comes from, what the verification ledger records, and what happens when one is found wrong.

The options

Correct As a standard change, implemented under the authorisation already granted to the documented procedure

Correct. A standard change is pre-authorised: the risk assessment and authorisation were done once, for the procedure, so each instance needs no fresh authorisation.

Not correct As a normal change, assessed and authorised individually each time it is requested

Wrong. Putting a low-risk, repeatable, fully documented activity through individual assessment is exactly the waste that the standard change type exists to remove.

Not correct As a standard change, but with the change authority re-confirming authorisation on each occurrence

Wrong, and this is the most tempting distractor. Re-authorising each occurrence contradicts the meaning of 'pre-authorised' and would make the standard change type pointless.

Not correct As an emergency change, because provisioning must be completed before the joiner's start date

Wrong. A known deadline is not an emergency. Emergency changes are for situations that must be resolved as soon as possible, such as restoring a service or applying an urgent security fix.

Why

Standard changes are low-risk, well-understood, fully documented and pre-authorised. The risk assessment happens once, when the procedure is created and approved; individual instances then proceed without further authorisation, and are often initiated as service requests. Requiring per-instance authorisation would defeat the purpose of the category.

Where this comes from

Cited
ITIL 4 syllabus clause 7

Practise this

Reading one question is not practice. The trainer will draw a short set from objective 7 and space the ones you get wrong.

Practise ITIL 4 Foundation

More questions on this objective

All questions on Seven ITIL practices in detail

Practise ITIL 4 Foundation