Which statement about the authorisation of a standard change is correct?

ITIL 4 Foundation, objective 7. Seven ITIL practices in detail medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

How these questions are written — where each question comes from, what the verification ledger records, and what happens when one is found wrong.

The options

Not correct A change advisory board must review and approve each occurrence before it is implemented

Wrong. Routing every occurrence through a board is precisely what the pre-authorised category avoids; a board reviewing repetitive low-risk work adds delay without adding control.

Correct Authorisation is granted in advance to the documented procedure itself, so no separate approval is needed when it is carried out

Correct. The authorisation attaches to the pre-approved procedure, which is why standard changes can be triggered and completed without a per-occurrence decision.

Not correct No risk assessment is ever performed for a standard change

Wrong. Risk was assessed — just once, when the procedure was created and approved. 'Pre-authorised' means the assessment happened earlier, not that it never happened.

Not correct Authorisation is granted after implementation, once the outcome is known

Wrong. Retrospective authorisation is not how standard changes work. Even emergency changes, which are the most compressed, are authorised before implementation by an expedited route.

Why

'Pre-authorised' is the defining property of a standard change: the assessment and the authorisation decision were made once, for the procedure, and every conforming instance inherits them. That is different from saying no assessment happened, and different from a board approving each occurrence.

Where this comes from

Cited
ITIL 4 syllabus clause 7

Practise this

Reading one question is not practice. The trainer will draw a short set from objective 7 and space the ones you get wrong.

Practise ITIL 4 Foundation

More questions on this objective

All questions on Seven ITIL practices in detail

Practise ITIL 4 Foundation