To keep a steering report looking healthy, a manager asks the Developers to mark items as done when the code is merged and to record the remaining test work as separate items in a later Sprint. Reported completion rises to ninety-five per cent. What is the effect in Scrum terms?
Professional Scrum Master I, objective 3. Managing products with agility hard
Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.
Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.
The options
Not correct It is acceptable, because the remaining work is still visible in the Product Backlog as its own items
Wrong, and it is the sharpest distractor here because the work genuinely is written down somewhere. The report still says finished when the product is not, and that is the number decisions are made on.
Not correct It is a reporting matter outside Scrum, since Scrum does not define steering reports
Wrong. Scrum does not define the report, but it does define the artefact the report describes, and an Increment that overstates what is finished is a Scrum problem wherever the number is printed.
Not correct It is acceptable if the Definition of Done is amended to match the new practice
Wrong. Weakening the Definition of Done to fit the report lowers quality rather than raising completion, and during the Sprint quality does not decrease. Where the organisation already carries a Definition of Done as a standard, no Scrum Team may drop below it either.
Correct It destroys the transparency of the Increment, and decisions based on a misleading artefact diminish value and increase risk
Correct. The Increment is one of the three artefacts on which important decisions are based, and inspecting an artefact that misstates its own state is worse than not inspecting at all.
Why
Transparency is not an honesty virtue in Scrum; it is a precondition for the whole empirical loop. Important decisions are based on the perceived state of the artefacts, so an Increment reported as more complete than it is quietly corrupts every decision downstream — what to release, what to fund, what to promise a customer. Inspection without transparency is misleading and wasteful. A pleasant number that describes nothing real costs more value than the bad news it was invented to avoid.
Where this comes from
- Cited
- Scrum Guide section Transparency
- What it says
- Artifacts that have low transparency can lead to decisions that diminish value and increase risk.
Practise this
Reading one question is not practice. The trainer will draw a set from objective 3 and space the ones you get wrong.
Practise Professional Scrum Master I
More questions on this objective
- A portfolio manager has drawn up a spreadsheet ranking every requested feature by projected revenue and tells the Scrum Team to build them in that order. The Product Owner believes two of the top five items will not be used by the customers she has spoken to. Who is accountable for maximising the value of the product? machine-checked
- It is the last afternoon of the Sprint. Three of the eight selected items are coded and demonstrable on a laptop, but they have not been through the automated regression suite the Definition of Done requires. The Product Owner suggests showing them at tomorrow's Sprint Review anyway, marked as "pending test". What does Scrum say? machine-checked
- A new Scrum Master is asked by a director where in Scrum the organisation gets to see whether the last four weeks of work were worth anything, and what should change as a result. Which event is she describing? machine-checked
- A Scrum Team spent a Sprint building a bulk-import feature. It meets the Definition of Done, it is usable, and it was released on day nine. At the Sprint Review the stakeholders explain that since the Sprint began their largest customer has moved to a different data format, and nobody will use the feature. What does Scrum say about this Sprint, and what happens now? machine-checked
- A delivery manager introduces a quarterly target: every Scrum Team must raise its velocity by fifteen per cent, and team performance reviews will cite the number. Within two Sprints the team's story point totals have risen and no more working software is reaching users than before. What is the most accurate statement about this measure? machine-checked
- A Scrum Team is agreeing what it will actually put in front of stakeholders at the end of each Sprint. Which TWO of the following statements about the Increment are true in Scrum? machine-checked