A critical service has failed and a fix must be applied as soon as possible. Which statement correctly describes how change enablement treats this emergency change?

ITIL 4 Foundation, objective 7. Seven ITIL practices in detail medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

How these questions are written — where each question comes from, what the verification ledger records, and what happens when one is found wrong.

The options

Not correct It must wait for the next scheduled change authority meeting so that it can be assessed properly

Wrong. Waiting for the routine cycle defeats the point of the emergency type; the expedited route exists so urgent work does not queue behind the calendar.

Not correct Assessment and authorisation are waived entirely, because urgency overrides control

Wrong. This is the dangerous misreading. Compressing an assessment is not the same as abandoning it — an unassessed emergency fix is how one incident becomes two.

Not correct It is reclassified as a standard change so that it can proceed under existing pre-authorisation

Wrong. Standard changes are pre-authorised precisely because they are routine, documented and low risk. An unplanned urgent fix meets none of those conditions.

Correct Assessment and authorisation are compressed and expedited, often through a separate change authority, rather than skipped

Correct. Emergency changes still require authorisation; the difference is speed. Organisations typically nominate a smaller, faster change authority so a decision can be reached quickly.

Why

Emergency changes must be implemented as soon as possible — to resolve an incident or apply an urgent security fix, for example. What changes is the tempo, not the existence of control: assessment and authorisation are expedited, frequently via a distinct change authority, and testing or documentation may be reduced or completed afterwards. Authorisation is never simply omitted.

Where this comes from

Cited
ITIL 4 syllabus clause 7

Practise this

Reading one question is not practice. The trainer will draw a short set from objective 7 and space the ones you get wrong.

Practise ITIL 4 Foundation

More questions on this objective

All questions on Seven ITIL practices in detail

Practise ITIL 4 Foundation