An organisation publishes a Definition of Done that all its products must meet. In a Retrospective, one Scrum Team decides it wants to add accessibility testing and a documented rollback plan to its own Definition of Done, which the organisational standard does not mention. A programme manager objects that the standard is the standard. Who is right?

Professional Scrum Master I, objective 2. Developing people and teams hard

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Not correct The programme manager — a team may not vary an organisational Definition of Done in either direction

Wrong. The standard binds as a floor, not as a ceiling. Freezing it in both directions would make it impossible for a team to raise quality for its own product, which is much of what a Retrospective is for.

Correct The team — an organisational Definition of Done must be followed as a minimum, so a team may hold itself to more

Correct. The word doing the work in the Guide is "minimum". Adding to it still complies; removing from it does not.

Not correct The team, and it may equally drop parts of the organisational standard that do not suit this product

Wrong, and it is the trap, because it looks like the same principle applied symmetrically. A minimum can be exceeded and never reduced, so dropping a clause takes the team below the standard.

Not correct Neither — the Product Owner sets the Definition of Done, so it is their decision

Wrong. The Definition of Done is not a Product Owner artefact. Where there is no organisational standard, the Scrum Team creates one appropriate for the product.

Why

Two sentences of the Guide settle every Definition of Done question of this shape. If the organisation has a standard, all Scrum Teams follow it as a minimum; if it does not, the Scrum Team must create one appropriate for the product. So a team's self-management over quality runs upward only. Note also what happens with several teams on one product: they must mutually define and comply with the same Definition of Done.

Where this comes from

Cited
Scrum Guide section Commitment: Definition of Done
What it says
If the Definition of Done for an increment is part of the standards of the organization, all Scrum Teams must follow it as a minimum.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 2 and space the ones you get wrong.

Practise Professional Scrum Master I

More questions on this objective

All questions on Developing people and teams