A new Scrum Master inherits a team where nobody admits to being stuck. They print the five values as posters, run a half-day workshop and ask everyone to sign a values charter on the wall. Three Sprints later nothing has changed. What does Scrum actually say about how the values take hold?

Professional Scrum Master I, objective 1. Understanding and applying the Scrum framework medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Not correct The values have to be taught and accepted before a team can start using Scrum, so the workshop was the right first step and simply needs repeating

Wrong. Scrum says successful use depends on people becoming more proficient in the values — proficiency that grows through use, not a threshold to clear before the first Sprint.

Correct Team members learn and explore the values as they work with the Scrum events and artifacts, so the lever is the events themselves

Correct. The values are learned in the doing: a Retrospective where naming a problem costs the person nothing teaches openness in a way a charter cannot. What a team observes about the consequences of speaking up in a real event will always outweigh what it signed on a poster.

Not correct The values apply to the Developers, since they are the ones doing the work; a Product Owner or Scrum Master is not measured against them

Wrong. The values describe the Scrum Team, and Scrum extends openness to its stakeholders as well. A Product Owner who withholds bad news undermines the same process a silent Developer does.

Not correct The values are a nice-to-have — what matters is that the events, artifacts and accountabilities are followed precisely

Wrong, and it is the answer a compliance-minded organisation reaches for. Successful use of Scrum depends on people living the values; when they are embodied, the pillars come to life building trust, and without that a team can hold every event and still hide everything that matters.

Why

The values are not a preface to Scrum, they are what the framework produces when it is run honestly — and what makes it work when it is. Commitment, focus, openness, respect and courage are explored through the events and artifacts, and their pay-off is named: embodied by the team and the people around it, they bring the pillars to life and build trust. So diagnose a values problem by looking at what the events reward, not at what the team was told.

Where this comes from

Cited
Scrum Guide section Scrum Values
What it says
The Scrum Team members learn and explore the values as they work with the Scrum events and artifacts.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 1 and space the ones you get wrong.

Practise Professional Scrum Master I

More questions on this objective

All questions on Understanding and applying the Scrum framework