A portfolio office asks a Scrum Team when the remaining forty Product Backlog items will be finished. The Developers extend their burn-up chart, and the office wants the resulting date entered in the plan as a delivery commitment. What is the accurate position in Scrum?

Professional Scrum Master I, objective 1. Understanding and applying the Scrum framework hard

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Not correct Charts of this kind have no place in Scrum, because Scrum defines no metrics and no forecasting practices

Wrong. Scrum names burn-downs, burn-ups and cumulative flows and calls them proven useful. The framework does not forbid them; it refuses to let them stand in for evidence.

Not correct Once the Definition of Done is stable and the team's throughput is steady, the projected date can be reported as a commitment

Wrong, and it is the tempting one because both conditions sound like the marks of a mature team. Stability of past measurement says nothing about what the next forty items will reveal, and in complex work what will happen is unknown.

Correct The projection is a forecast that each Sprint's evidence is expected to revise — only what has already happened may be used for forward-looking decision making

Correct. The chart is a legitimate aid and a legitimate answer to give, provided it is offered as the extrapolation of observed work that it is, and re-drawn every Sprint as new observations arrive.

Not correct The Scrum Master should produce the forecast, as a neutral party accountable for the Scrum Team's effectiveness

Wrong. Effectiveness is served by enabling the team to improve its own practices, not by taking over its judgements. A forecast about the work belongs to the people who will do the work.

Why

Scrum is unusually careful here: forecasting practices are useful and they do not replace empiricism. The distinction that survives the exam room is between a projection and a promise. A projection is drawn from what has already been observed and is expected to move; a promise asks future evidence to conform to a number set before the evidence existed. Scrum permits the first freely and has no mechanism for the second: what the Sprint Backlog carries as its commitment is the Sprint Goal, an objective, not a date.

Where this comes from

Cited
Scrum Guide section The Sprint
What it says
Only what has already happened may be used for forward-looking decision making.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 1 and space the ones you get wrong.

Practise Professional Scrum Master I

More questions on this objective

All questions on Understanding and applying the Scrum framework