A known error has been recorded with a workaround in place. The team periodically re-examines its impact, the cost of the incidents it causes, and whether a permanent fix has become worthwhile. Which phase of problem management is this?

ITIL 4 Foundation, objective 7. Seven ITIL practices in detail hard

Draft — not checked yet. This question was written from the published exam objectives and cites the clause it comes from, but nobody has yet read it against that clause and signed for it.

It is kept out of search results and out of mock exams until they have. Read the source below before you take the answer as settled.

The options

Not correct Change enablement

A change request may well come out of this activity, but raising and assessing that change is a different practice. The re-assessment itself belongs to problem management.

Not correct Problem control

Problem control is the earlier phase where the problem is analysed and workarounds and known errors are documented. Once a known error exists, ongoing management of it moves to error control.

Not correct Problem identification

Identification is about discovering that a problem exists at all. This problem was found and analysed some time ago.

Correct Error control

Correct. Error control manages known errors after analysis: it identifies potential permanent solutions, which may lead to a change request, and it re-assesses known errors and the effectiveness of their workarounds over time.

Why

The dividing line between the two control phases is the known error. Problem control produces analysis, workarounds and known error records; error control then owns those known errors, periodically reconsidering the cost-benefit case for a permanent solution as circumstances change.

Where this comes from

Cited
ITIL 4 syllabus clause 7
What it says
Error control manages known errors, identifies potential permanent solutions which may result in a change request, and re-assesses known errors and workarounds.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 7 and space the ones you get wrong.