With a large launch two weeks away, the Developers propose skipping the Sprint Retrospective for the next two Sprints — "we know what is wrong, we just have no time to talk about it". The Product Owner agrees. What should the Scrum Master do?

Professional Scrum Master I, objective 2. Developing people and teams medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Not correct Agree, because a self-managing team may decide how it works

Wrong, and it is the strongest distractor because it invokes a genuine Scrum principle. Self-management governs how the team does its work inside the framework; it does not extend to deleting a part of the framework.

Not correct Hold the Retrospective anyway and run it himself while the Developers keep working

Wrong. An event the team is not in is not the event; the Retrospective is the Scrum Team inspecting itself, and one person cannot do it on their behalf.

Correct Ensure the Retrospective still takes place, and use the pressure the team is under as its subject so the event is demonstrably productive

Correct. The Scrum Master ensures all Scrum events take place and are positive, productive and within the timebox — and a team too busy to improve is precisely the team that needs the event.

Not correct Replace it with an anonymous survey for the two Sprints so no meeting time is lost

Wrong. A survey collects opinions but produces no shared inspection and no agreed improvement for the next Sprint, which is what the event is for.

Why

Events are where inspection and adaptation actually happen, so skipping one is a lost opportunity to adapt, not a saved hour. The Scrum Master's accountability here is specific — the events take place, are positive and productive, and stay within the timebox — and the second half matters as much as the first. If a team wants to drop an event, the useful question is what makes it feel worthless, and that question is itself Retrospective material.

Where this comes from

Cited
Scrum Guide section Scrum Master
What it says
Ensuring that all Scrum events take place and are positive, productive, and kept within the timebox.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 2 and space the ones you get wrong.

Practise Professional Scrum Master I

More questions on this objective

All questions on Developing people and teams