A programme office has instructed stakeholders that all questions for the Scrum Team must go through a delivery liaison, who collects them and forwards a weekly summary. Two Sprints later the Developers say they no longer understand who they are building for. What should the Scrum Master do about the arrangement?

Professional Scrum Master I, objective 2. Developing people and teams medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Not correct Leave it in place but ask the liaison to forward questions daily rather than weekly

Wrong. Speeding up a relay does not restore the conversation; the Developers still never hear a stakeholder's own words or ask their own follow-up question.

Not correct Ask the Product Owner to answer every stakeholder question personally so the liaison becomes unnecessary

Wrong, and it is a near miss — the Product Owner does represent stakeholder needs in the Product Backlog, but making one person the sole channel rebuilds the same barrier with a different name.

Correct Work with the programme office to remove the barrier, so stakeholders and the Scrum Team talk to each other directly

Correct. Removing barriers between stakeholders and Scrum Teams is one of the named ways a Scrum Master serves the organisation, and this arrangement is exactly such a barrier.

Not correct Record the loss of contact as an impediment in the Sprint Retrospective and move on

Wrong. Naming it in a Retrospective is a reasonable start, but the accountability does not end at documenting an impediment the team cannot remove by itself.

Why

Empiricism needs the people who receive the work and the people doing it to be in contact — that is what makes the Increment inspectable by the people whose opinion decides its value. Layers of relay are usually installed for good reasons, protecting the team's focus or a manager's overview, and they quietly starve the team of the information Scrum runs on. Serving the organisation means going to whoever built the layer and taking it out, not routing around it.

Where this comes from

Cited
Scrum Guide section Scrum Master
What it says
Removing barriers between stakeholders and Scrum Teams.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 2 and space the ones you get wrong.

Practise Professional Scrum Master I

More questions on this objective

All questions on Developing people and teams