During one Sprint the Developers complete work meeting the Definition of Done on four separate days. At the Sprint Review a stakeholder asks how many Increments the Sprint produced. What is the accurate answer in Scrum terms?

Professional Scrum Master I, objective 1. Understanding and applying the Scrum framework medium

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Correct Four — multiple Increments may be created within a Sprint, each additive to the ones before it, and the sum of them is what is presented at the Sprint Review

Correct. An Increment is created by meeting the Definition of Done, not by reaching the end of the Sprint, so a Sprint can produce several and often does.

Not correct One — an Increment is by definition what a Sprint produces

Wrong, and it is a habit left over from how Scrum used to be taught. A Sprint produces at least one usable Increment, and nothing limits it to one.

Not correct None yet — the work becomes an Increment when it is accepted at the Sprint Review

Wrong. An Increment is born the moment a Product Backlog item meets the Definition of Done, and there is no acceptance step at the Sprint Review to wait for.

Not correct Four were created, but only the last one counts, because each Increment supersedes the one before

Wrong. Increments are additive rather than replacements: each is added to all prior Increments and thoroughly verified so that they all work together.

Why

Increments accumulate. Each one is a concrete stepping stone toward the Product Goal, additive to everything already built and verified against it, and any of them may go to stakeholders before the Sprint ends. The Sprint Review presents the sum of them to support empiricism — it is where the accumulated result gets inspected, not the moment the result comes into existence.

Where this comes from

Cited
Scrum Guide section Increment
What it says
Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 1 and space the ones you get wrong.

Practise Professional Scrum Master I

More questions on this objective

All questions on Understanding and applying the Scrum framework