Which THREE of these does the Sprint Retrospective inspect, as Scrum describes the event?

Professional Scrum Master I, objective 1. Understanding and applying the Scrum framework hard

Machine-checked — no person has signed for it. This question was read against the source cited below by an automated pass, which found no contradiction. That is a weaker claim than it sounds: the same kind of process wrote the question, so it can confirm its own mistake.

Treat it as a good draft rather than as settled fact, and read the source below before you rely on it. It is not used in mock exams here — only questions a person has signed for are.

The options

Choose 3.

Correct How the last Sprint went with regard to individuals and interactions

Correct. Individuals and interactions are named explicitly, which is what makes the Retrospective a conversation about people and not only about process.

Correct The processes and tools the Scrum Team used

Correct. Tooling is in scope: a two-day wait for a shared environment is exactly the kind of thing the event exists to surface and then remove.

Correct The Definition of Done

Correct, and it is the one people miss. The Retrospective is where the team asks whether its quality bar is still right for the product — which is why the Definition of Done is not renegotiated during Sprint Planning.

Not correct The ordering of the Product Backlog

Wrong event. Product Backlog ordering is the Product Owner's decision, informed by what stakeholders say at the Sprint Review. The Retrospective inspects how the team works, not what the product should do next.

Not correct Whether each Developer met their individual performance objectives

Wrong. Scrum sets no individual objectives and inspects none. Introducing them turns an event that depends on candour into one where nobody can afford to name a mistake.

Why

The Retrospective inspects how the last Sprint went with regard to individuals, interactions, processes, tools and the Definition of Done, and Scrum adds a step teams often skip: identifying the assumptions that led them astray and exploring where those assumptions came from. Cause, not just symptom. The Definition of Done sitting on that list is the detail worth carrying into the exam.

Where this comes from

Cited
Scrum Guide section Sprint Retrospective
What it says
The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done.

Practise this

Reading one question is not practice. The trainer will draw a set from objective 1 and space the ones you get wrong.